CS作业代写 Project Management in IT

Project Management in IT
IT Project Cost: Tools, Techniques
Semester 1, 2022 Dr Rabiul University of 1
Schwalbe, K, Information Technology Project Management (9th Edition). Cengage Learning, 2019

Copyright By PowCoder代写 加微信 powcoder

Recapture From Lecture 3
We discussed IT Project Time: Tools, Techniques
 Time Management  Network Diagram  CPM
The University of 2

What Will We Do Today ?
– Plan Cost Management – Estimate Cost
– Determine Budget
– Control Costs
 Class activities
– Critical Thinking / Problem Solving
– Tools to use: https://padlet.com https://answergarden.ch
 Assessment
– Test: Knowledge Test is in week 7
– Assignment: Group project is due in week 10, Sunday midnight
 Announcement (if any): ?
– Tutorial: All teams will work on their group projects during the
tutorials.
The University of 3

Learning Objectives
 Discuss the importance of project cost management
 Explain basic project cost management principles, concepts,
 Describe the processes of planning cost management
 Discuss the processes of determining a budget
The University of 4

What is Cost?
 Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange
 Costs are usually measured in monetary units like dollars
The University of 5

Project Cost Management
 Project cost management includes the processes required to ensure that the project is completed within an approved budget
 IT projects have a poor track record for meeting budget goals. Why?
The University of 6

Project Cost Management Overview
The University of : A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 7

Project Cost Management Processes
 Planning cost management: determining the policies, procedures, and documentation that will be used for planning, executing, and controlling project cost.
 Estimating costs: developing an approximation or estimate of the costs of the resources needed to complete a project
 Determining the budget: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance
 Controlling costs: controlling changes to the project budget
The University of 8

Financial Terms To Use
 Most members of an executive board better understand and are more interested in financial terms than IT terms, so IT project managers must speak their language (financial terms)
– Profitsarerevenuesminusexpenditures
– Profitmarginistheratioofrevenuestoprofits,netincomedividedby
revenue, or net profits divided by sales
– Lifecyclecostingconsidersthetotalcostofownership,ordevelopment plus support costs, for a project
– Cashflowanalysisdeterminestheestimatedannualcostsandbenefits for a project and the resulting annual cash flow
The University of 9

Costs and Benefits
 Tangible costs or benefits are those costs or benefits that an organization can easily measure in dollars
 Intangible costs or benefits are costs or benefits that are difficult to measure in monetary terms
 Direct costs are costs that can be directly related to producing the products and services of the project
 Indirect costs are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project
 Sunk cost is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs
The University of 10

What Is Reserve?
 Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict
– Contingencyreservesallowforfuturesituationsthatmaybepartially planned for (sometimes called known unknowns) and are included in the project cost baseline
– Managementreservesallowforfuturesituationsthatareunpredictable (sometimes called unknown unknowns
The University of 11

Planning Cost Management
 The project team uses expert judgment, analytical techniques, and meetings to develop the cost management plan
 A cost management plan includes:
– Levelofaccuracyandunitsofmeasure – Organizationalprocedurelinks
– Controlthresholds
– Rulesofperformancemeasurement
– Reportingformats
– Processdescriptions
The University of 12

Planning Cost Management
The University of : A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 13

Estimating Costs
 Project managers must take cost estimates seriously if they want to complete projects within budget constraints
 It’s important to know:
– the types of cost estimates,
– how to prepare cost estimates,
– typical problems associated with IT cost estimates
The University of 14

Estimating Costs
The University of : A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 15

Estimating Costs — Tools and Techniques  Basic tools and techniques for cost estimates:
– Analogousortop-downestimates:usetheactualcostofaprevious, similar project as the basis for estimating the cost of the current project
– Bottom-upestimates:involveestimatingindividualworkitemsor activities and summing them to get a project total
– Parametricmodelingusesprojectcharacteristics(parameters)ina mathematical model to estimate project costs
The University of 16

Estimating Costs — Issues with IT Projects
 Estimates are done too quickly
 People lack estimating experience
 Human beings are biased toward underestimation  Management desires accuracy
The University of 17

Things to Know for Cost Estimate
 Know what it will be used for,
 Gather as much information as possible,
 Clarify the ground rules and assumptions for the estimate
 If possible, estimate costs by major WBS categories
 Create a cost model to make it easy to make changes to and
document the estimate
The University of 18

Sample Cost Estimate
The University of 19

Determining the Budget
 Cost budgeting involves allocating the project cost estimate to individual work items over time
 The WBS is a required input to the cost budgeting process since it defines the work items
 Important goal is to produce a cost baseline
– atime-phasedbudgetthatprojectmanagersusetomeasureandmonitor
cost performance
The University of 20

Determining the Budget
The University of : A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 21

Project Budget Components
The University of : A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 22

Cost Baseline – Sample Project
The University of 23

Controlling Costs
 Project cost control includes
– Monitoringcostperformance
– Ensuringthatonlyappropriateprojectchangesareincludedina revised cost baseline
– Informingprojectstakeholdersofauthorizedchangestotheprojectthat will affect costs
The University of 24

Controlling Costs
The University of : A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 25

Earned Value Management (EVM)
 Earned value management (EVM) is a technique that combines scope, time, cost and resource measurements to assess project performance and progress.
 You must enter actual information periodically to use EVM
 It is a common method of measuring performance of projects
The University of from: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 26

Earned Value Management
 The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period
 Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period
 The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed
 EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date
The University of 27

Earned Value Management
 Schedule variance (SV) is a measure of schedule performance expressed as the difference between the earned value and the planned value. Equation: SV = EV – PV
 Cost variance (CV) is the amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and the actual cost. Equation: CV= EV − AC.
 The schedule performance index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value. Equation: SPI = EV/PV
 The cost performance index (CPI) is a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost. Equation: CPI = EV/AC
The University of : A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 28

Understanding Earned Value Numbers
 Negative numbers for cost and schedule variance indicate problems in those areas
 CPI and SPI less than 100% indicate problems
 Problems mean the project is costing more than planned (over
budget) or taking longer than planned (behind schedule)
 The budget at completion (BAC) is the original total budget for the project
 The CPI can be used to calculate the estimate at completion (EAC = BAC/CPI )—an estimate of what it will cost to complete the project based on performance to date.
The University of 29

Earned Value Calculation
Your budgeted cost of an IT project is $100,000, and it needs to be completed in 6 months. After two months of completion, you, as an IT project manager, wish to assess the project performance and progress. You have found that your team has completed 30% of the project works and spent $40,000. At this stage, your planned completion is 35%. How is your project performing?
Budget at Completion (BAC)= 100,000
AC = 40,000
PV = Planned Completion (%) * BAC = 35% * $100,000 = $35,000 EV = Actual Completion (%) * BAC = 30% * $100,000 = $30,000
CPI=EV/AC = 30,000/40,000 = 0.75, this means that for every 1 dollar your team spent, the project is producing only 75% of project work.
SPI= EV/PV = 30,000/35,000 = 0.86, this means that for every hour of work, the project team is completing only 0.86 hours.
Performance: ?
The University of 30

IT Project appraisal – decision-making
Q: Which project should your organization choose?
Net Present Value (NPV) Benefit Cost Ratio (BCR) Budget/Cost
IT Project
Budget/Cost
The University of 31

Group Exercise — Cost Modeling, Baseline
 Prepare cost model for the project. Use the WBS provided, and be sure to document your assumptions in preparing the cost model.
 Assume a labor rate of $100/hour for the project manager and $60/hour for other project team members.
 Assume that none of the work is outsourced, labor costs for users are not included, and there are no additional hardware costs. The total estimate should be $200,000.
The University of 32

(a) Cost Modeling
The University of 33

(b) Cost Baseline
 Using the cost model you created earlier, prepare a cost baseline by allocating the costs by WBS for each month of the project.
 The following is a sample structure provided to guide you, your team may choose a different structure.
The University of 34

Class Quiz
 What would you need to determine the budget for your project?
The University of 35

Scenario Analysis
High-cost IT projects by Australian Govt.
 Review the scenario of “High-cost IT projects by Australian Govt.”, refer to week 4 module on Canvas and answer the questions.
Q1: What are the issues with the Government-funded high-cost IT projects regarding project cost management?
Rooms (): write your response here https://docs.google.com/document/d/1tqQGq20wJB8L9jqdp1tZJd9dqNZ-
i8YfTiIOdlFYdfw/edit?usp=sharing
Q2: As an IT project manager, what would you like to recommend to improve the situation?
Rooms (): write your response here https://docs.google.com/document/d/1fdhRlb0Bor9EqjIyt3lDKwEiF3ZnTaeS0T
MG0XcDFUA/edit?usp=sharing
The University of 36

Discussion on Group Projects
The University of 37

Lecture Summary
 Project cost management is a traditionally weak area of IT projects, and project managers must work to improve their ability to deliver projects within approved budgets
 Project cost management processes include – Plancostmanagement
– Estimatecosts
– Determinethebudget
– Controlcosts