CS计算机代考程序代写 INFO3333

INFO3333
Computing 3 Management
Lecture 4
Managing IT Project: Cost
Semester 1, 2021 Dr Rabiul Hasan
The University of Sydney
Page 1
Source:
Schwalbe, K, Information Technology Project Management (9th Edition). Cengage Learning, 2019

Recapture From Lecture 3
We discussed Managing IT Project: Time
 Time Management  Network Diagram  CPM
 PERT
The University of Sydney
Page 2

Where Are We Now ? — Course map
The University of Sydney Page 3

What Will We Do Today ?
 Lecture
– Plan Cost Management – Estimate Cost
– Determine Budget
– Control Costs
 Class activities
– Critical Thinking / Problem Solving – Tools to use: https://padlet.com
https://answergarden.ch
 Assessment
– Tutorial: No separate practices provided during the tutorials in
weeks 5-8 . All teams will work on their group projects. – Assignment: Group project is due in week 8
 Announcement (if any): ?
The University of Sydney Page 4

Learning Objectives
 Discuss the importance of project cost management
 Explain basic project cost management principles, concepts,
and terms
 Describe the processes of planning cost management
 Discuss the processes of determining a budget
The University of Sydney
Page 5

What is Cost?
 Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange
 Costs are usually measured in monetary units like dollars
The University of Sydney Page 6

Project Cost Management
 Project cost management includes the processes required to ensure that the project is completed within an approved budget
 IT projects have a poor track record for meeting budget goals. Why?
Write your response here
https://docs.google.com/document/d/1X22Qs-mtIKwlxN- ygDPkpQqOg-w8o5rlHSYKGgnrtAw/edit?usp=sharing
The University of Sydney Page 7

Project Cost Management Overview
The University of Sydney Source: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 8

Project Cost Management Processes
 Planning cost management: determining the policies, procedures, and documentation that will be used for planning, executing, and controlling project cost.
 Estimating costs: developing an approximation or estimate of the costs of the resources needed to complete a project
 Determining the budget: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance
 Controlling costs: controlling changes to the project budget
The University of Sydney Page 9

Financial Terms To Use
 Most members of an executive board better understand and are more interested in financial terms than IT terms, so IT project managers must speak their language (financial terms)
– Profitsarerevenuesminusexpenditures
– Profitmarginistheratioofrevenuestoprofits,netincomedividedby
revenue, or net profits divided by sales
– Lifecyclecostingconsidersthetotalcostofownership,ordevelopment plus support costs, for a project
– Cashflowanalysisdeterminestheestimatedannualcostsandbenefits for a project and the resulting annual cash flow
The University of Sydney Page 10

Costs and Benefits
 Tangible costs or benefits are those costs or benefits that an organization can easily measure in dollars
 Intangible costs or benefits are costs or benefits that are difficult to measure in monetary terms
 Direct costs are costs that can be directly related to producing the products and services of the project
 Indirect costs are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project
 Sunk cost is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs
The University of Sydney Page 11

What Is Reserve?
 Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict
– Contingencyreservesallowforfuturesituationsthatmaybepartially planned for (sometimes called known unknowns) and are included in the project cost baseline
– Managementreservesallowforfuturesituationsthatareunpredictable (sometimes called unknown unknowns
The University of Sydney Page 12

Planning Cost Management
 The project team uses expert judgment, analytical techniques, and meetings to develop the cost management plan
 A cost management plan includes:
– Levelofaccuracyandunitsofmeasure – Organizationalprocedurelinks
– Controlthresholds
– Rulesofperformancemeasurement
– Reportingformats
– Processdescriptions
The University of Sydney
Page 13

Planning Cost Management
The University of Sydney Source: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 14

Estimating Costs
 Project managers must take cost estimates seriously if they want to complete projects within budget constraints
 It’s important to know:
– the types of cost estimates,
– how to prepare cost estimates,
– typical problems associated with IT cost estimates
The University of Sydney
Page 15

Estimating Costs
The University of Sydney Source: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 16

Estimating Costs — Tools and Techniques  Basic tools and techniques for cost estimates:
– Analogousortop-downestimates:usetheactualcostofaprevious, similar project as the basis for estimating the cost of the current project
– Bottom-upestimates:involveestimatingindividualworkitemsor activities and summing them to get a project total
– Parametricmodelingusesprojectcharacteristics(parameters)ina mathematical model to estimate project costs
The University of Sydney Page 17

Estimating Costs — Issues with IT Projects
 Estimates are done too quickly
 People lack estimating experience
 Human beings are biased toward underestimation  Management desires accuracy
The University of Sydney
Page 18

Things to Know for Cost Estimate
 Know what it will be used for,
 Gather as much information as possible,
 Clarify the ground rules and assumptions for the estimate
 If possible, estimate costs by major WBS categories
 Create a cost model to make it easy to make changes to and
document the estimate
The University of Sydney Page 19

Sample Cost Estimate
The University of Sydney Page 20

Sample Cost Estimate — Software Development
The University of Sydney Page 21

Determining the Budget
 Cost budgeting involves allocating the project cost estimate to individual work items over time
 The WBS is a required input to the cost budgeting process since it defines the work items
 Important goal is to produce a cost baseline
– atime-phasedbudgetthatprojectmanagersusetomeasureandmonitor
cost performance
The University of Sydney Page 22

Determining the Budget
The University of Sydney Source: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 23

Project Budget Components
The University of Sydney Source: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 24

Cost Baseline – Sample Project
The University of Sydney Page 25

Controlling Costs
 Project cost control includes
– Monitoringcostperformance
– Ensuringthatonlyappropriateprojectchangesareincludedina revised cost baseline
– Informingprojectstakeholdersofauthorizedchangestotheprojectthat will affect costs
The University of Sydney Page 26

Controlling Costs
The University of Sydney Source: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 27

Earned Value Management (EVM)
 Earned value management (EVM) is a technique that combines scope, time, cost and resource measurements to assess project performance and progress.
 You must enter actual information periodically to use EVM
 It is a common method of measuring performance of projects
The University of Sydney Adapted from: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 28

Earned Value Management
 The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period
 Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period
 The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed
 EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date
The University of Sydney Page 29

Earned Value Management
 Schedule variance (SV) is a measure of schedule performance expressed as the difference between the earned value and the planned value. Equation: SV = EV – PV
 Cost variance (CV) is the amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and the actual cost. Equation: CV= EV − AC.
 The schedule performance index (SPI) is a measure of schedule efficiency expressed as the ratio of earned value to planned value. Equation: SPI = EV/PV
 The cost performance index (CPI) is a measure of the cost efficiency of budgeted resources, expressed as a ratio of earned value to actual cost. Equation: CPI = EV/AC
The University of Sydney Source: A Guide to the Project Management Body of Knowledge, Fifth Edition (PMBOK® Guide) © 2013 Project Management Institute Page 30

Understanding Earned Value Numbers
 Negative numbers for cost and schedule variance indicate problems in those areas
 CPI and SPI less than 100% indicate problems
 Problems mean the project is costing more than planned (over
budget) or taking longer than planned (behind schedule)
 The budget at completion (BAC) is the original total budget for the project
 The CPI can be used to calculate the estimate at completion (EAC = BAC/CPI )—an estimate of what it will cost to complete the project based on performance to date.
The University of Sydney Page 31

Earned Value Calculation
Your budgeted cost of an IT project is $100,000, and it needs to be completed in 6 months. After two months of completion, you, as an IT project manager, wish to assess the project performance and progress. You have found that your team has completed 30% of the project works and spent $40,000. At this stage, your planned completion is 35%. How is your project performing?
Budget at Completion (BAC)= 100,000
AC = 40,000
PV = Planned Completion (%) * BAC = 35% * $100,000 = $35,000 EV = Actual Completion (%) * BAC = 30% * $100,000 = $30,000
CPI=EV/AC = 30,000/40,000 = 0.75, this means that for every 1 dollar your team spent, the project is producing only 75% of project work.
SPI= EV/PV = 30,000/35,000 = 0.86, this means that for every hour of work, the project team is completing only 0.86 hours.
Performance: ?
The University of Sydney Page 32

IT Project appraisal – decision-making
Q: Which project should your organization choose?
Net Present Value (NPV) Benefit Cost Ratio (BCR) Budget/Cost
IT Project
NPV
B/C ratio
Budget/Cost
Project A
70,000
1.01
200,000
Project B
72,000
1.12
250,000
Project C
80,000
1.20
300,000
The University of Sydney
Page 33

Group Exercise — Cost Modeling, Baseline, Cash Flow
 Prepare cost model for the project. Use the WBS provided, and be sure to document your assumptions in preparing the cost model.
 Assume a labor rate of $100/hour for the project manager and $60/hour for other project team members.
 Assume that none of the work is outsourced, labor costs for users are not included, and there are no additional hardware costs. The total estimate should be $200,000.
The University of Sydney
Page 34

(a) Cost Modeling
The University of Sydney Page 35

(b) Cost Baseline
 Using the cost model you created earlier, prepare a cost baseline by allocating the costs by WBS for each month of the project.
 The following is a sample structure provided to guide you, your team may choose a different structure.
The University of Sydney Page 36

(c) Cash Flow
 Your team should now develop a cash flow table. The following is a sample structure provided to guide you, you may choose a different structure.
The University of Sydney Page 37

Class Quiz
 What would you need to determine the budget for your project?
 Write your response here: https://docs.google.com/document/d/16LF79F49etAwtrzMwUL3
xHsG44bLl3t1tAcem9EAkrM/edit?usp=sharing
The University of Sydney Page 38

Scenario Analysis
 Review the scenario of Self-driving Uber Issue, in week 4 module on Canvas
Room A: write your response here https://docs.google.com/document/d/1SP46mIufH20BkBUK3KTX
SFfLaCM9kumSMuTMv4j6VXQ/edit?usp=sharing
Room B: write your response here https://docs.google.com/document/d/1rPf-4APbFX5-
LAf7CRb409LIkHAxv7wpxF7Ysi32ghE/edit?usp=sharing
The University of Sydney Page 39

Discussion on Group Projects
The University of Sydney Page 40

Lecture Summary
 Project cost management is a traditionally weak area of IT projects, and project managers must work to improve their ability to deliver projects within approved budgets
 Project cost management processes include – Plancostmanagement
– Estimatecosts
– Determinethebudget
– Controlcosts
The University of Sydney
Page 41