PowerPoint Presentation
Information Technology
FIT2002
IT Project Management
Lecture 10 (Part 2)
Monitoring and Controlling
Learning Objectives
Understand what is meant by monitoring and control
Understand the integrated change control process
Understand how to monitor and control schedule and cost
issues
A revisit of Earned Value Management (EVM)
2
3Source: PMBOK® Guide, Sixth Edition, 2017.
Mapping Project Management Process
Groups to Knowledge Areas
Initiating Planning Executing
Monitoring &
Controlling
Closing
Project Integration
Management
1. Develop Project
Charter
2. Develop Project
Management Plan
3. Direct & manage
project work
4. Manage Project
Knowledge
5. Monitor & control
project work
6. Close Project or
Phaase
Project Scope
Management
1. Plan Scope
Management
2.. Collect requirements
3. Define Scope
4. Create WBS
5. Validate Scope;
6. Control Scope
Project Schedule
Management
1. Plan Schedule
Management
2. Define Activities
3. Sequence Activities
4. Estimate Activity
Durations
5. Develop Schedule
6. Control Schedule
Project Cost
Management
1. Plan Cost
Management
2. Estimate Costs
3. Determine Budget
4. Control Costs
Knowledge Areas
Project Management Process Group
Continued…
4
Initiating Planning Executing
Monitoring &
Controlling
Closing
Project Quality
Management
1. Plan Quality
Management
2. Manage Quality 3. Control Quality
Project Resource
Management
1. Plan Resource
Management
2. Estimate Activity
Resources
3. Acquire Resources
4. Develop Team
5. Manage Team
6. Control Resources
Project
Communication
Management
1. Plan Communications
Management
2. Manage
Communications
3. Monitor
Communications
Project Risk
Management
1. Plan Risk Management
2. Identify Risks
3. Perform Qualitative
Risk Analysis
4. Perform Quantitative
Risk Analysis
5. Plan Risk Responses
6. Implement Risk
Responses
7. Monitor Risks
Project
Procurement
Management
1. Plan Procurement
Management
2. Conduct
Procurements
3. Control
Procurements
Project Stakeholder
Management
1. Identify
Stakeholders
2. Plan Stakeholder
Management
3. Manage
Stakeholder
Engagement
4. Monitor
Stakeholder
Engagement
Knowledge Areas
Project Management Process Group
Source: PMBOK® Guide, Sixth Edition, 2017.
Monitoring & Control
Monitoring and Control processes are used to measure and
report progress, handle changes to scope, time, cost, and
quality, manage the project team, manage risk mitigation
strategies, and monitor procurement contracts
Process overlap
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 5
Monitoring Vs. Control
Monitoring is collecting and reporting information
concerning previously defined project performance
elements
Control uses the information supplied by the monitoring
techniques in order to bring project actual results in line
with stated project performance standards
6Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press
Keys to Effective Monitoring and Controlling
The organisation and project manager must foster an
environment that allows for the honest reporting of results
To reduce the chances for biased reporting the process should
be as automated as possible and there needs to be a separation
of responsibilities
Time must be allocated in the project schedule to perform the
tasks of monitoring and control
Lastly, all members of the project team, stakeholders, and other
management resources should receive training on effective
monitoring and control techniques
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 7
Integration Management Processes
Develop the Project Charter
Develop the project management plan
Direct and manage project execution
Monitor and control the project work: Oversee project work to
meet the performance objectives of the project
Perform integrated change control: Coordinate changes that
affect the project’s deliverables and organisational process
assets
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 8
Integrated Change Control
(refer to lecture 3 video 4)
A formal process used to approve and manage all necessary project
document and deliverable changes
Key activities
– Identifying that a change needs to occur or has occurred
– Establishing a governance structure for reviewing and
approving requested changes
– Managing the approved changes when and as they occur
– Maintaining the integrity of project artifacts, as changes occur
– Communication to all relevant stakeholders
– Configuration management
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 9
Project Cost Management Processes
Plan Cost Management
Estimate costs
Determine budget
Control Cost: controlling changes to the project budget
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 10
Cost Control
Is concerned with:
– influencing the factors that create cost variances on the
project and
– controlling changes to the project’s budget
Like the other monitoring and control processes, cost control is
a continual process of comparing the current actual project
expenditures to the defined budget and determining when
issues have arrived that need to be dealt with
Almost every change made on an IT project will affect Cost
in some manner
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 11
Earned Value Management (EVM)
A technique used to help determine and manage project
progress and the magnitude of any variations from the planned
values concerning cost, schedule, and performance
The technique was created to help the project team and
stakeholders gain a better understanding of just how the project
is performing
Many project managers fail to evaluate performance properly
– How much work has actually been completed and how
much work actually remains
– Not necessarily how many hours have been worked
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 12
Percent Complete
Often times IT projects can be difficult to estimate progress
– 0-100 percent rule
– 50-50 percent rule
– Interval percent rule (0, 25, 50, 75, 100)
13Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press
EVM Key Values
Recall from Lecture 6…
Planned Value (PV) – is the budgeted cost for the work
scheduled to be completed on a task, work package, or activity
up to a given point in time (BCWS)
Actual Cost (AC) – is the total cost incurred in accomplishing
work on the task during a given time period (ACWP)
Earned Value (EV) – is the budgeted amount for the work
actually completed on the task during a given time period or EV =
(PV)*(percent complete) (BCWP)
14Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press
EVM Key Values
Cost Variance (CV) – equals earned value (EV) minus actual cost
(AC) or CV = EV – AC
Schedule Variance (SV) – equals earned value (EV) minus
planned value (PV) or SV = EV – PV
Cost Performance Index (CPI) = equals the ratio of EV to the AC,
or CPI = EV/AC
– Equal to 100% then Actual = Planned
– Less than 100% then project is over budget
Schedule Performance Index (SPI) – equals the ratio of EV to the
PV, or SPI = EV/PV
– Equal to 100% then Actual = Planned
– Less than 100% project is behind schedule
15Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press
PV, AC and EV
16
Brewer (2013). Methods of Information Technology Management .p.365.
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press
Planned value (PV)
17
Planned Value (PV) – is the budgeted cost for the work scheduled
to be completed on a task, work package, or activity up to a given point
in time
Also referred to as the budgeted cost of work scheduled (BCWS).
The final PV of a task is equal to the task’s budget at completion
(BAC), i.e. the total amount budgeted for the task.
Assessment Date
Budget at Completion (BAC)
$
Planned Value (PV)
0 1 2 3 4 5
Time
Source: http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
$X
http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
Earned value (EV)
18
Earned Value (EV) – is the budgeted amount for the work
actually completed on the task during a given time period (BCWP)
– EV = (Project Budget)*(percent complete)
Also referred to as the budgeted cost of work performed (BCWP).
0 1 2 3 4 5
Assessment Date
Budget at Completion (BAC)
$
Planned Value (PV)
Earned Value (EV)
Time
Source: http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
$Y
http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
Actual Cost (AC)
19
Actual Cost (AC) – is the total cost incurred in accomplishing work
on the task during a given time period
Also referred to as the actual cost of work performed (ACWP).
0 1 2 3 4 5
Assessment Date
Budget at Completion (BAC)
$
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Time
Source: http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
$Z
http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
Example
Q. A project has a budget of $10M and schedule for 10 months. It is assumed
that the total budget will be spent equally each month until the 10th month is
reached. After 2 months the project manager finds that only 5% of the total work
is finished and a total of $1M spent.
Find out how the project is progressing in terms of schedule and budget.
Budgeted Cost scheduled for each month is = $10M/10 months = $1M
Planned Value (BCWS) = $2M
Earned Value (BCWP) = $10M * 5% = $0.5M
Actual Cost (ACWP) = $1M
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 20
Cost Variance (CV)
21
Shows whether and by how much the project is under or over the approved budget.
Negative CV means the project is over the budget (cost overrun).
Positive CV means the project is below the budget.
This is the actual dollar value by which a project is either overrunning or under
running its estimated cost.
0 1 2 3 4 5
Assessment Date
Budget at Completion (BAC)
$
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Time
Cost Variance
(Under Budget)
CV = EV –AC
Source: http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
Cost Performance Indicator (CPI)
22
CPI showing the project’s cost efficiency or the utilisation of the resources on the
project.
Equal to 100% then Actual = Planned
Less than 100% then project is over the budget
More than 100% then project is below the budget
CPI = EV /AC
Source: http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
0 1 2 3 4 5
Assessment Date
Budget at Completion (BAC)
$
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Time
Cost Variance
(Under Budget)
http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
Schedule Variance (SV)
23
SPI shows whether your work is ahead of or behind your approved schedule.
Negative SV means the project is behind schedule
Positive SV means the project is ahead of schedule
SV is calculated in terms of the difference in dollar value between the amount of
work that should have been completed in a given time period and the work actually
completed.
Schedule Variance
(Behind Schedule by
1 Month)
$
0 1 2 3 4 5
Assessment Date
Budget at Completion (BAC)
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Time
SV = EV – PV
Source: http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
Schedule Performance Indicator (SPI)
24
SPI indicates the rate at which the project is progressing (ahead of or behind
schedule), and is sometimes referred to as the project’s schedule efficiency.
Equal to 100% then Actual = Planned
Less than 100% project is behind schedule
More than 100% project is ahead of schedule
SPI = EV / PV
Source: http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
Schedule Variance
(Behind Schedule by
1 Month)
$
0 1 2 3 4 5
Assessment Date
Budget at Completion (BAC)
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
Time
http://www.dummies.com/how-to/content/earned-value-management-terms-and-formulas-for-pro.html
EXAMPLE– Cost/Budget
25
Q. A project has a budget of $10M and schedule for 10 months. It is assumed
that the total budget will be spent equally each month until the 10th month is
reached. After 2 months the project manager finds that only 5% of the total work
is finished and a total of $1M spent.
Find out how the project is progressing in terms of schedule and budget.
PV = $2M EV = $0.5M AC = $1M
CV = EV – AC
= 0.5 – 1
= – 0.5M (Cost overrun)
CPI = EV / AC
= 0.5 / 1
= 0.5 (Cost overrun)
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press
Example – Schedule
26
Q. A project has a budget of $10M and schedule for 10 months. It is assumed that the total
budget will be spent equally each month until the 10th month is reached. After 2 months the
project manager finds that only 5% of the total work is finished and a total of $1M spent.
Find out how the project is progressing in terms of schedule and budget.
PV = $2M EV = $0.5M AC = $1M
SV = EV – PV
= 0.5 – 2
= –$1.5M (Behind schedule)
SPI = EV / PV
= 0.5 / 2
= 0.25 (Behind schedule)
Currently we are 75% behind schedule i.e. (1–SPI)*100%, since we have only achieved
25% of the schedule.
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press
More EVM Key Values
BAC Budget at Completion
– How much did you BUDGET for the Total Job?
ETC Estimate to Complete
– From this point on, how much MORE do we expect it to
cost to finish the job?
– ETC = (BAC- EV)/CPI
EAC Estimate at Completion
– What do we currently expect the TOTAL project to cost?
– EAC = AC + ETC
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 27
EVM Terms Visually
Brewer (2018). Methods of Information Technology Management .p.364.
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 28
Example – Schedule part 2
Q. A project has a budget of $10M and schedule for 10 months. It is assumed
that the total budget will be spent equally each month until the 10th month is
reached. After 2 months the project manager finds that only 5% of the total work
is finished and a total of $1M spent.
Find out how the project is progressing in terms of schedule and budget.
PV = $2M EV = $0.5M AC = $1M CPI = 0.5
Budget at completion (BAC) = $10m
Estimate to complete (ETC) = (BAC – EV) / CPI = (10 – 0.5) / 0.5 = $19m
Estimate at Completion (EAC) = ETC + AC = 19 + 1 = $20m
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 29
Report Performance
Report Performance – collecting and disseminating
performance information
Performance reporting involves the collection of all project
and product related data and the distribution of
performance information to stakeholders
Project related data includes information from all areas of
the project including: schedule, costs, quality, risks,
human resources, and if needed procurement
The frequency of the reports (daily, weekly, monthly) is
determined by the type of report, size of the project and
the importance of the project as stated in the
communication plan
30
Performance Report Categories
Progress reports – physical progress to date, Actual
data vs. planned data
Status reports – identify where the project is today (the
date the report is prepared) and the information from
collected performance data to calculate Schedule
Variance and Cost Variance
Projection reports – calculate the following
Earned Value numbers – Estimate at Completion
(EAC), Estimate to Complete (ETC), Schedule
Performance Index (SPI), and Cost Performance Index
(CPI).
The report is forward looking giving
projections/forecasts of the project finish
Exception reports – exceptions, problems, risks
31
Final Thoughts on EVM
The results are only as good as the data accuracy
If numbers generated in a timely fashion, allows the project
manager to act in a proactive manner instead of a reactive mode
Make sure to establish rules for progress reporting (percent
complete) early in the project then communicate and educate all
project team members for consistency across all tasks
Brewer J, Dittman K (2018), Methods of IT Project Management (3e), Purdue University Press 32