Project Management in IT
IT Project Methods and Requirements Gathering Strategies
Semester 1, 2022 Dr Rabiul University of 1
Schwalbe, K, Information Technology Project Management (9th Edition). Cengage Learning, 2019
Copyright By PowCoder代写 加微信 powcoder
Recapture From Lecture 1
It was an overview of PM in IT:
Attributes of a Project
Why Project or Project Management? IT Project Management
IT Project Manager
PMBOK Knowledge Areas Project Life Cycle
The University of 2
Learning Objectives
Discuss Project Management Methodologies
Understand project goal, objectives, deliverables, and scope
Describe and understand the processes of project scope management
Discuss methods of investigating and collecting requirements to meet stakeholder needs and expectations
Discuss the process for creating a work breakdown structure
Discuss and understand the importance and method of validating
and controlling project scope
The University of 3
Project Management Methodologies
A methodology is a system of practices, techniques, procedures and rules used by those who work in a discipline.
Popular PM Methodologies:
– Waterfall Project Management – Agile Project Management
The University of 4
Waterfall Project Management
Traditional, or “waterfall” project management handles things sequentially, from the concept and planning phase through to development and quality assurance and finally project completion and maintenance.
Waterfall methodology is most often applied to large software development projects as thorough planning and predictability are supreme to the project process and success.
The University of : (Katcherovski, 2012). (Baker, n.d.) Page 5
Agile Project Management
Agile project management focuses on adaptability to changing situations and constant, regular feedback – whether it’s from the client or from other members of the team.
This is ideal when clients or management need to be in on the production process, resulting in changing requirements and drastic shifts in team assignments.
Agile project management is usually ideal for smaller software projects and/or those with accelerated development schedules.
The University of : Katcherovski, 2012 Page 6
Agile Project Management … continue
Agile means being able to move quickly and easily, but some people feel that project management, as they have seen it used, does not allow people to work quickly or easily.
Early software development projects often used a waterfall approach. As technology and businesses became more complex, the approach was often difficult to use because requirements were unknown or continuously changing.
Agile today means using a method based on iterative and incremental development, in which requirements and solutions evolve through collaboration.
The University of 7
Agile Project Management … continue Agile Scope Management
– Scope is not well understood, but needs to be controlled Agile Time Management
– Schedule must be flexible due to changes Agile Cost Management
– Costs are more difficult to estimate Agile Risk Management
– Higher risk aspects of project are completed first Agile Quality Management
– Quality assessed after each iteration
The University of Analysis and Design in a Changing World, 7th Edition – Chapter 11, ©2016. Cengage Learning. All rights reserved. Page 8
An iterative project management methodology that thrives in situations where requirements constantly shift (Icasas, 2014).
Scrum is part of the Agile movement.
The Scrum approach to agile software development marks a
dramatic departure from waterfall management.
Scrum and other agile methods were inspired by shortcomings of waterfall method.
Scrum emphasizes collaboration, functioning software, team self management, and the flexibility to adapt to emerging business realities.
The University of : http://scrummethodology.com/ Page 9
PRINCE2 is a government-endorsed project management methodology, released and supported by the UK government in 1996.
It is a very process-oriented methodology, dividing projects into multiple stages, each with their own plans and processes to follow (Katcherovski, 2012).
The University of 10
Critical Thinking Exercise 1: Managerial Perspectives Q1: Which Project Management Method should you choose?
– With short time schedule
Please write your answer here at AnswerGarden. Write ONE WORD Only
https://answergarden.ch/2367258
Q2: Which Project Management Method should you choose? – With unclear user requirements
Please write your answer here at AnswerGarden. Write ONE WORD Only
https://answergarden.ch/2367259
The University of 11
Project Goal, Objectives, Deliverable, and Scope
Project Goal: Long-term
Objectives: Short-term and practical
A deliverable is a product produced as part of a project, such as hardware or software, planning documents, or meeting minutes
Scope refers to all the work involved in creating the products of the project and the processes used to create them.
The University of 12
Project Scope Management Overview
Source: A Guide to the Project Management Body of
The University of (PMBOK® Guide) – Fifth Edition Page 13
Project Scope Management Processes:
(1) Plan Scope Management
Plan Scope Management is the process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled
The University of : A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition Page 14
Scope Management Plan Contents
How to prepare a detailed project scope statement
How to create a WBS
How to maintain and approve the WBS
How to obtain formal acceptance of the completed project
deliverables
How to control requests for changes to the project scope
The University of 15
Project Scope Management Processes:
(2) Collect Requirements
Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.
The University of : A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition Page 16
Requirements Management Plan
The PMBOK describes requirements as “conditions or capabilities that must be met by the project or present in the product, service, or result to satisfy an agreement or other formally imposed specification”
The requirements management plan documents how project requirements will be analyzed, documented, and managed
The University of 17
Collect Requirements
For some IT projects, it is helpful to divide requirements development into categories called elicitation, analysis, specification, and validation
It is important to use an iterative approach to defining requirements since they are often unclear early in a project
The University of 18
Relative Cost to Correct a Software Requirement Defect
The University of 19
Methods for Collecting Requirements
Interviewing
Focus groups and facilitated workshops
Using group creativity and decision-making techniques
Questionnaires/surveys
Observation
Prototyping
Benchmarking, or generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization, can also be used to collect requirements
The University of 20
Requirements Traceability Matrix
A requirements traceability matrix (RTM) is a table that lists requirements, various attributes of each requirement, and the status of the requirements to ensure that all requirements are addressed
Sample entry in an RTM
The University of 21
Project Scope Management Processes
(3) Define Scope
Define Scope is the process of developing a detailed description of the project and product.
The University of : A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition Page 22
Define Scope
Project Charter
Scope Statement
The University of : A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Sample Project Charter (partial)
The University of 24
Scope Statement
Project scope statements should include at least a product scope description, product user acceptance criteria, and detailed information on all project deliverables.
As time progresses, the scope of a project should become more clear and specific
The University of 25
Project Scope Management Processes:
(4) Create WBS
Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components.
The University of : A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition Page 26
Creating the Work Breakdown Structure (WBS)
A WBS is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project
WBS is a foundation document that provides the basis for planning and managing project schedules, costs, resources, and changes
Decomposition is subdividing project deliverables into smaller pieces
A work package is a task at the lowest level of the WBS
The scope baseline includes the approved project scope
statement and its associated WBS and WBS dictionary
The University of 27
WBS Organized by Product
The University of 28
WBS Organized by Phase
The University of 29
WBS Organized in Tabular Form
The University of 30
Intranet WBS and in Microsoft Project
The University of 31
Intranet Organized by Project Management Process Groups
The University of 32
Detailed WBS for Executing Section (Process)
The University of 33
Approaches to Developing WBSs
Using guidelines: Some organizations, like the Department of Defense (DOD), provide guidelines for preparing WBSs
The analogy approach: Review WBSs of similar projects and tailor to your project
The top-down approach: Start with the largest items of the project and break them down
The bottom-up approach: Start with the specific tasks and roll them up
Mind-mapping approach: Mind mapping is a technique that uses branches radiating out from a core idea to structure thoughts and ideas
The University of 34
Mind-Mapping Approach for Creating a WBS
The University of 35
The WBS Dictionary
Many WBS tasks are vague and must be explained more so people know what to do and can estimate how long it will take and what it will cost to do the work
A WBS dictionary is a document that describes detailed information about each WBS item
The University of 36
WBS Dictionary
The University of 37
Things to Remember for Creating a WBS
A unit of work should appear at only one place in the WBS.
The work content of a WBS item is the sum of the WBS items
A WBS item is the responsibility of only one individual, even though many people may be working on it
The WBS must be consistent with the way in which work is actually going to be performed; it should serve the project team first, and other purposes only if practical
The University of 38
Things to Remember for Creating a WBS (cont’d)
Project team members should be involved in developing the WBS to ensure consistency and buy-in
Each WBS item must be documented in a WBS dictionary to ensure accurate understanding of the scope of work included and not included in that item
The WBS must be a flexible tool to accommodate inevitable changes while properly maintaining control of the work content in the project according to the scope statement
The University of 39
Project Scope Management Processes:
(5) Validate Scope
Validate Scope is the process of formalizing acceptance of the completed project deliverables.
The University of : A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition Page 40
Validating Scope
It is very difficult to create a good scope statement and WBS for a project
It is even more difficult to verify project scope and minimize scope changes
Scope validation involves formal acceptance of the completed project deliverables
Acceptance is often achieved by a customer inspection and then sign-off on key deliverables
The University of 41
Scope Management Issues
Many countries have had difficulties controlling the scope of large projects, especially those that involve advanced technologies and many different users
For example, the state government of Victoria, Australia, has a Web site for its public transportation smart card at https://www.ptv.vic.gov.au/
There were many problems in developing and implementing the smart card
How about ? Or any other projects?
Did you experience any issues on user requirements?
The University of 42
Project Scope Management Processes:
(6) Control Scope
Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline.
The University of : A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition Page 43
Controlling Scope
Scope control involves controlling changes to the project scope
Goals of scope control are to
– controlthefactorsthatcausescopechanges
– assurechangesareprocessedaccordingtoproceduresdevelopedas part of integrated change control, and
– managechangeswhentheyoccur
The University of 44
Lecture Summary
Project scope management includes the processes required to ensure that the project addresses all the mandatory work, to complete the project successfully
Scope Management processes include – Planscopemanagement
– Collect requirements
– Definescope
– CreateWBS
– Validate scope – Controlscope
The University of 45